Framatome's steam generator replacement expertise supports long-term operations in Canada by Staff Writers Paris, France (SPX) Aug 05, 2021
Steam generator replacements were a hot topic and in high demand in the U.S. during the late 1990s and early 2000s. Utilities across the country contracted with the Steam Generating Team (SGT), a partnership between Framatome and United Engineers and Constructors, to implement their large component replacement projects. Over 25 years, SGT replaced steam generators at 24 units, nine reactor vessel closure heads and one pressurizer. As the need for these replacements slowed down in the U.S., new opportunities emerged in Canada. With regulatory approval to pursue life extension programs for the Canadian operating fleet, utility customers defined nuclear refurbishment projects to extend the operating life of their plants. In 2017, the Steam Generator Replacement Team (SGRT), a joint venture between SGT and Aecon, contracted with Bruce Power to replace steam generators at Unit 6 of the Bruce Nuclear Generating Station. SGRT also signed a long-term Preferred Supplier Agreement that defined a structure for contracting steam generator replacements at the plant's remaining five units as part of its Major Component Replacement (MCR) Project. This arrangement positioned SGRT as Bruce Power's long-term strategic partner through 2032, offering the customer deep bench-strength of experience, certainty of supply, innovation, and technology advancements, along with an established long-term presence in the Bruce Power community.
Major outage ongoing at Bruce Power Unit 6 Additionally, SGRT completed the design phase for the second unit (Unit 3) at the Bruce Power site planned to undergo refurbishment. "One of the biggest challenges the project team faces to date is the COVID-19 pandemic," said Curtis Van Cleve, president of Framatome Canada Ltd. "When it comes to a large-scale project like a steam generator replacement, there's a long-term and robust schedule with key milestones and deliverables for both the project team and for the customer. It has been challenging to maintain the implementation schedule as we deal with COVID-19 restrictions. Our access to the customer site and to our own facilities and colleagues that support us remotely is limited. The project team has done an excellent job of maintaining high-quality execution to overcome these challenges."
A new contract for Units 3 and 4 This win directly results from the solid delivery of engineering and implementation work on Unit 6 by all parties involved in SGRT. It is a testament to the commitment of these teams in the face of the challenges presented this past year. These teams persevered and worked closely with the customer to ensure the continued operational excellence of this groundbreaking project. Further collaborations are expected to enhance the long-term operations of the Canadian nuclear fleet.
Proven expertise on all types of technologies The multi-unit Bruce Power MCR Project is extremely important to Framatome and to SGRT. Framatome replaced various steam generator designs in the U.S. and Europe and now adds the first CANDU reactor to its portfolio of expertise. As Framatome and its partners continue to execute replacements at the remaining Bruce Power units, they will build on lessons learned and enhance performance with each subsequent replacement.
GE Hitachi awarded long-term outage services contract by Leibstadt Nuclear Power Plant Wilmington NC (SPX) Jul 30, 2021 The Leibstadt Nuclear Power Plant (KKL) has awarded a long-term contract extension to GE Hitachi Nuclear Energy (GEH) to provide outage services for the plant in Leibstadt, Switzerland. "We have supported KKL with outage and inspection services since it went into operation in 1984 and we are proud to continue this strong working relationship," said John Mackleer, Senior Vice President, Field Services for GEH. Under the extension, which runs through 2030, GEH will continue to provide a full p ... read more
|
|
The content herein, unless otherwise known to be public domain, are Copyright 1995-2024 - Space Media Network. All websites are published in Australia and are solely subject to Australian law and governed by Fair Use principals for news reporting and research purposes. AFP, UPI and IANS news wire stories are copyright Agence France-Presse, United Press International and Indo-Asia News Service. ESA news reports are copyright European Space Agency. All NASA sourced material is public domain. Additional copyrights may apply in whole or part to other bona fide parties. All articles labeled "by Staff Writers" include reports supplied to Space Media Network by industry news wires, PR agencies, corporate press officers and the like. Such articles are individually curated and edited by Space Media Network staff on the basis of the report's information value to our industry and professional readership. Advertising does not imply endorsement, agreement or approval of any opinions, statements or information provided by Space Media Network on any Web page published or hosted by Space Media Network. General Data Protection Regulation (GDPR) Statement Our advertisers use various cookies and the like to deliver the best ad banner available at one time. All network advertising suppliers have GDPR policies (Legitimate Interest) that conform with EU regulations for data collection. By using our websites you consent to cookie based advertising. If you do not agree with this then you must stop using the websites from May 25, 2018. Privacy Statement. Additional information can be found here at About Us. |