France's Areva to pay 600 mn euros more for Finnish reactor
by AFP Staff Writers
Helsinki (AFP) May 17, 2021

A new nuclear reactor under construction in Finland will cost a consortium led by French firm Areva another 600 million euros to complete, Finnish energy company TVO said Monday.

TVO, which will operate the plant once it is built, and Areva "reached a consensus regarding the terms of the OL3 EPR project completion" including the payment worth $730 million, the company said.

Sited at Olkiluoto in southeast Finland, the EPR plant has been under construction for almost 16 years, and is set to start feeding power into the grid in February 2022.

Ground was broken in 2004 and the reactor was initially supposed to be finished by 2009, but it has been plagued by delays like similar projects in Britain and northern France.

Now fuelled and almost ready to begin electricity production in October, it will supply almost 15 percent of Finland's energy at 1,650 megawatts.

"This money won't go to TVO, it's money that will be spent on finishing the project," the Finnish company's chief executive Jarmo Tanhua told AFP.

TVO said there could be an "additional compensation" from Areva if the start date was delayed again.

map/eb/tgb/jj

AREVA


Related Links
Nuclear Power News - Nuclear Science, Nuclear Technology
Powering The World in the 21st Century at Energy-Daily.com


Thanks for being here;
We need your help. The SpaceDaily news network continues to grow but revenues have never been harder to maintain.

With the rise of Ad Blockers, and Facebook - our traditional revenue sources via quality network advertising continues to decline. And unlike so many other news sites, we don't have a paywall - with those annoying usernames and passwords.

Our news coverage takes time and effort to publish 365 days a year.

If you find our news sites informative and useful then please consider becoming a regular supporter or for now make a one off contribution.
SpaceDaily Contributor
$5 Billed Once


credit card or paypal
SpaceDaily Monthly Supporter
$5 Billed Monthly


paypal only


CIVIL NUCLEAR
Framatome to complete upgrades at Krsko Nuclear Power Plant in Slovenia
Paris, France (SPX) May 17, 2021
Framatome recently signed two contracts to upgrade systems and equipment used to manage operations at the Krsko Nuclear Power Plant in Slovenia. The company will design, deliver and install new instrumentation and control (I and C) systems and replace the thimble tubes, which are an important part of the plant's in-core neutron flux measurement system. "For our work with the Krsko Nuclear Power Plant, our team brings a unique focus on our customer's need to modernize the plant and extensive engine ... read more

Comment using your Disqus, Facebook, Google or Twitter login.



Share this article via these popular social media networks
del.icio.usdel.icio.us DiggDigg RedditReddit GoogleGoogle

CIVIL NUCLEAR
Can lab-grown algae help tackle hunger?

US waives clean fuel rules to alleviate shortage after pipeline shutdown

Will your future clothes be made of algae?

Incentives could turn costs of biofuel mandates into environmental benefits

CIVIL NUCLEAR
Renewable energy powers ahead in 2020: report

Space weather and solar blobs

Researchers unveil roadmap to expand NY solar energy, meet green goals

Closing in on state-of-the-art semiconductor solar cells

CIVIL NUCLEAR
US approves its biggest offshore wind farm yet

Vertical turbines could be the future for wind farms

Researchers working to further develop monopile production for offshore wind farms

Blowing in the wind: Fishermen threaten South Korea carbon plans

CIVIL NUCLEAR
German govt approves more ambitious emissions targets

Germany's struggling Social Democrats push green credentials

Spanish parliament approves clean energy bill

Millions at risk as cities fail to adapt to climate change: report

CIVIL NUCLEAR
Renewable energy sources: On the way towards large-scale thermal storage systems

Electric vehicle batteries: The older they get, the safer they are

Denmark's largest battery - one step closer to storing green power in stones

On course to create a fusion power plant

CIVIL NUCLEAR
Seven killed in landslide at Indonesia gold mine

Asian cities face perfect storm of environmental hazards

E-waste recycling matter of national security: report

French court dismisses case over Agent Orange use in Vietnam War

CIVIL NUCLEAR
Flared natural gas latest prize in bitcoin miners' energy quest

Canada asks US court to block shutdown of Line 5 pipeline

Saudi official in Baghdad, a month after Iran talks

Asian stocks mixed after US jobs miss, oil up after cyber attack

CIVIL NUCLEAR
Volcanoes on Mars could be active, raise possibility of recent habitable conditions

Why Ingenuity's fifth flight will be different

NASA's Ingenuity Helicopter to begin new demonstration phase

NASA extends Mars helicopter mission to assist rover









The content herein, unless otherwise known to be public domain, are Copyright 1995-2024 - Space Media Network. All websites are published in Australia and are solely subject to Australian law and governed by Fair Use principals for news reporting and research purposes. AFP, UPI and IANS news wire stories are copyright Agence France-Presse, United Press International and Indo-Asia News Service. ESA news reports are copyright European Space Agency. All NASA sourced material is public domain. Additional copyrights may apply in whole or part to other bona fide parties. All articles labeled "by Staff Writers" include reports supplied to Space Media Network by industry news wires, PR agencies, corporate press officers and the like. Such articles are individually curated and edited by Space Media Network staff on the basis of the report's information value to our industry and professional readership. Advertising does not imply endorsement, agreement or approval of any opinions, statements or information provided by Space Media Network on any Web page published or hosted by Space Media Network. General Data Protection Regulation (GDPR) Statement Our advertisers use various cookies and the like to deliver the best ad banner available at one time. All network advertising suppliers have GDPR policies (Legitimate Interest) that conform with EU regulations for data collection. By using our websites you consent to cookie based advertising. If you do not agree with this then you must stop using the websites from May 25, 2018. Privacy Statement. Additional information can be found here at About Us.